..Believes country is over-exposed
The Federal Government is seeking $1 billion to enable work to continue on a gas pipeline costing up to $2.8 billion after Chinese lenders failed to disburse cash as quickly as expected.

China reportedly developed cold feet after they pledged to offer most of the funds. It is the latest sign of falling Chinese financial support for infrastructure projects across Africa, after years of major Chinese lending for railway, energy and other projects.
A spokesman for the NNPC, which is building the 614-km Ajaokuta-Kaduna-Kano (AKK) pipeline, said it was still negotiating with the Chinese lenders – Bank of China and Sinosure – to cover $1.8 billion of the project cost.
“There’s no cause for alarm”, the spokesman said, without saying whether NNPC was turning to other lenders.
But the three sources told Reuters the company was now approaching others, including export-import institutions, to continue work on the pipeline that will run through the middle of the West African country to its northern economic hub Kano.
Chinese lenders had originally been lined up to fund the bulk of the estimated $2.5bn to $2.8bn cost of the project, which is central to President Muhammadu Buhari’s plan to develop gas resources and boost development in northern Nigeria.
NNPC, which was funding 15%, said last year it had used its own funds to start construction.
The sources said the Chinese lenders would not agree to disburse the cash NNPC had expected by the end of the summer, prompting it to turn to others. “They are looking at Nigeria as one loan, and right now, they feel they are too exposed”, one source said.
The sources said the Chinese lenders would not agree to disburse the cash NNPC had expected by the end of the summer, prompting it to turn to others. “They are looking at Nigeria as one loan, and right now, they feel they are too exposed,” one source said.
Chinese bank lending to African infrastructure projects has fallen across the continent, from $11 billion in 2017 to $3.3 billion in 2020, a Baker McKenzie report said in April. As at March 2021, Nigeria had borrowed $3.7 billion from China, out of which it had paid back about $500million, leaving a balance of $3.2 billion.
It is not only the AKK gas project that China has developed cold legs in funding. It is also holding its funds from going to Nigerian ICT Infrastructure Backbone project Phase-2. The project, in 2018, was to cost $2.3 billion, with China fully funding it, but till now, no dime has been disbursed, three years after.
China loans only make up 10% of Nigeria’s total indebtedness estimated at $32bn by the Debt Management Office, (DMO).
The World Bank, IMF and development banks account for 54.7% of the debt. Bilateral loans, including from China are about 12.4%. Euro and Diaspora bonds are about 24%.
With the continent facing an estimated annual $100 billion infrastructure investment deficit, the loss of Chinese funding leaves a big gap to fill.